CAPM Sample Questions for Certified Associate in Project Management
- CertiMaan
- Oct 10
- 8 min read
Updated: 2 days ago
Ace your Certified Associate in Project Management (CAPM) exam with these carefully crafted CAPM sample questions. Covering key domains like project integration, scope, schedule, cost, and stakeholder management, these practice questions mirror the real exam format. Whether you're looking for a free CAPM practice test, updated dumps, or scenario-based exam questions, this resource is designed to boost your readiness. Use these sample questions to identify weak areas, reinforce your understanding, and improve time management under exam conditions. Ideal for entry-level project professionals, students, and aspiring PMs preparing for the CAPM certification. Stay confident and exam-ready with high-quality CAPM exam practice materials.
CAPM Sample Questions List :
1. You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?
$50,000
None of the above
$200,00
$0
2. During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.
Product analysis
"'s^ assessment
Alternative selection
Alternative identification
3. You are managing a project that will implement a new MARKETING software package. You have assigned the resources and want to keep the IT manager in the loop by informing him or her of your decisions. Which type of organizational structure are you working in?
Functional
Pi'ojectized
Weak Matrix
Strong Matrix
4. A Risk Register is a part of the ________.
Project Scope Statement
Project Charter
Project Management plan
Project Scheduling plan
5. Make-or-buy decisions measure the costs of both options. What are the two options?
Tactical and Strategic
Direct ar|d Indirect
Management and Project
0nly Tactical
6. The product description of a project can help to create procurement details. Which one of the following best describes product description?
The product description defines the requirements for the contract work
All of the above
The product description defines the contracted work
The product description defines the contracted work, based on the requirements of the project customer
7. Who is responsible for issuing the project charter?
The project manager
The nianagement
The Team lead
The project sponsor
8. A Risk Register is a part of the ________.
Project Management plan
Project Scheduling plan
Project Scope Statement
Project Charter
9. A complete set of indexed project records is called __________.
Project History
Project archives
sow
Index
10. Create Procurement document is done in _______.
Conduct Procurements
Close Procurements
Plan Procurements
Administer Procurements
11. Which of the following provides the least accurate in estimating?
WBS estimate
Budget estimate
Rough order of magnitude
Definitive estimate
12. You have been with the organization; you constantly hear rumours about a certain CAPM failing to live up to the CAPM Code. What you should do?
You can gather as much information as you can before proceeding
^ass the rumours along
Confront the person immediately
Ignore the rumours
13. What is the lowest level in a work breakdown structure?
Project task
w°rl< package
None
sow
14. Which of the following are the inputs of Define Scope?
Requirements document created in collect requirements process
Project files from previous projects
All of the above
Project Charter
15. A requirement document is an input of __________ process?
Collect Requirements
Monitor and Control Project Work
Integrated Change Control
Define Scope
16. Who has the responsibility for informing the final deliverable to all stakeholders?
Management
Team Lead
Project Manager
Sponsor
17. Projects are seeded from the recognition of a regulatory or business need. Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of benefits measurement methods when selecting a project. Best Option is A.
Improvement to the project scope
Schedule constraints
Regulatory constraints
Value added change (enhancements)
18. Which document is best suited for tracking the assignment of all resources to specific tasks in a project?
0 CPI
RACI mAl,x
Staffing management plan
sow
19. Which type of network diagram is also referred to activity-on-arrow (AOA) diagrams?
Gant Cnart Diagram (GCD)
Arrow Diagramming Method (ADM)
Precedence Diagramming Method (PDM)
Dependency Diagramming Method (DDM)
20. You are project manager of a project. During the process of selecting the sellers, you reject one vendor because it doesn't have the manufacturing capability. This is an example of which selection tool?
Screening system
Weighting system
Expert judgment
Seller rating system
21. A contract cannot contain _____________.
Penalties and fines for disclosure of intellectual rights
Illegal activities
deadline for the completion of the work
All of the above
22. At what point in a project do you have the highest probability that it will fail?
^ust before the end of the project
The beginning of the project
Execution phase
QA Phase
23. The work breakdown structure is ________.
Used to break down the project into manageable pieces
Set and does not change throughout the project
Needed as part of the project charter
Needed as part of the project scope statement
24. Assumptions are factors that, for planning purposes, are considered to be ______.
Verbal
True, real, or uncertain
True, real, or certain
Rea
25. If a project with a SPI of 1.8, what you tell?
None
The project is running behind of the schedule
Resources assigned to the project cost 1.8 units
The project is running ahead of the schedule
26. Who gives project acceptance?
Customer
Project Manager
Sponsor
Team Lead
27. Based on the PMBOK, who is ultimately responsible for the project quality?
Project manager
Project team
QA manager
Validation engineer
28. From whom do you need to gain the formal acceptance at project closure?
The qualify director
The customer
Project manager
Project management office
29. _________ is the international organization that controls the standards for quality.
ISO
PMI
iscn
CAPM
30. The end of the project comes after which of the following?
QA activities are done
Final deliverable
Project charter
Schedule
31. In which phase project manager is assigned to a project?
During the initiation stage
After the project is proven feasible
Your answer is incorrect
During the planning stage
After approval of budget
32. Which of the following technique to identify the underlying cause of a problem and take steps to prevent further occurrence?
Project audits
Root cause analysis
Quality audits
Risk audits
33. The Ishikawa diagram, Pareto chart, control charts, and statistical sampling are examples of ________.
Quality assurance
Quality control
Quality rules
CMM
34. ______________ provides details about how the project scope may be changed.
Scope Charter
VeiirV Scope
Scope Management plan
Control Scope system
35. Collect Requirements process starts in Project Planning Phase and uses the outputs of the __________.
Estimation Process
Project closer Process
Initiation Process
Closing process
36. Which one of the following comes first in the project plan?
Development Plan
Scope Statement
Quality Plan
WBS
37. You are project manager of a project and as part of the team acquisition process; you hire a new employee and assigns him to your project team. According to Maslow's hierarchy of needs, what needs level he most likely is at?
Social need
Physical need
Safety and security
Security
38. Project Quality Management includes:
All of the above
Continuous improvement
Customer satisfaction
Prevention over inspection
39. The intent of the risk management process group is to ________.
Announce project risks
Not consider risks affecting the company
Increase the probability of positive outcomes in the project
Announce project deliverables
40. What is a corrective action?
An action to correct something in the project
An action that brings future project events Into alignment with the project plan
An action to prevent something in the project
Corrective action is not related to project
41. Which of the following statement is true about project charter?
Announces who is the project engineer
Provides a high level definition of the effort and its stakeholders
Tells the newspapers and media when the project will end
Announces who is the project sponsor
42. You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?
Balanced matrix
Strong Matrix
Functional
Piojectized
43. Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?
None of the above
Parametric estimating
Funding limit reconciliation
Reserves analysis
44. Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of ____________.
Integral parts of the SOW
Ways to ensure stakeholder commitment
Project selection methods
Enterprise benefits measurement methods when selecting a project
45. Which of the following is an output of Verify Scope?
Rework
Formal acceptance
WBS template
sow acceptance
46. Administrative Closure should occur ___________.
At the end of 100% of the project
At the end of the whole project
At the end of 50% of the project
At the end of each phase of the project
47. PMI discusses procurement focusing on the ______ relationship.
Sellino
Purchasing
Buyer or seller
Vendor or seller
48. In PMBOK, the seller is ________ to the project team.
External
Assigned
Internal
Outside
49. You are project manager and now in middle of creating RFP (Request for proposal). RFP (Request for proposal) is done in _______.
Close Procurements
Administer Procurements
Plan Procurements
Conduct Procurements
50. Function of the __________ is to make sure that changes to anything in the project are recorded and agreed to by the stakeholders.
Team Lead
Project Manager
Management
Sponsor
FAQs
1. What is the Certified Associate in Project Management (CAPM) certification?
The CAPM is an entry-level certification from PMI that validates your understanding of project management principles, processes, and terminology.
2. How do I become CAPM certified?
You need to meet PMI’s eligibility requirements, apply on PMI.org, and pass the CAPM exam.
3. What are the eligibility requirements for the CAPM exam?
Secondary degree (high school diploma or equivalent)
23 hours of project management education or training
4. How much does the CAPM certification cost?
PMI members: $225 USD
Non-members: $300 USD
5. How many questions are on the CAPM exam?
The CAPM exam has 150 multiple-choice questions.
6. What is the passing score for the CAPM certification exam?
PMI does not disclose a fixed passing score; results are shown by proficiency levels.
7. What topics are covered in the CAPM exam?
Topics include project management fundamentals, predictive, adaptive, and hybrid approaches, and PMBOK® Guide knowledge areas.
8. How long is the CAPM exam and what is the format?
The exam lasts 3 hours and is computer-based.
9. How long does it take to prepare for the CAPM exam?
Most candidates prepare in 6–10 weeks, depending on prior experience.
10. What is the difficulty level of the CAPM exam?
It is considered easier than PMP but still requires thorough knowledge of project management basics.
11. Are there any CAPM sample questions or practice tests available?
Yes, PMI provides sample questions, and CertiMaan offers practice tests and dumps.
12. What is the validity period of the CAPM certification?
The CAPM certification is valid for 3 years.
13. How many PDUs are required to maintain the CAPM certification?
You need 15 PDUs every 3 years to renew.
14. Can I retake the CAPM exam if I fail?
Yes, you can attempt the exam up to 3 times within your one-year eligibility period.
15. What jobs can I get with a CAPM certification?
Typical roles include Project Coordinator, Junior Project Manager, Project Analyst, and PMO Associate.
16. How much salary can I earn with a CAPM certification?
On average, CAPM-certified professionals earn more than non-certified peers, often in the $50k–$80k range depending on role and country.
17. Is the CAPM certification worth it?
Yes. It helps beginners start a career in project management and enhances credibility.
18. What is the difference between CAPM and PMP certifications?
CAPM: Entry-level, focused on fundamentals.
PMP: Advanced-level, requires significant project management experience.
19. What are the best study materials for the CAPM exam?
Use PMI’s CAPM Exam Content Outline, PMBOK® Guide, and practice tests from CertiMaan.
20. Where can I register for the Certified Associate in Project Management exam?
You can register directly on the PMI website (pmi.org) by submitting your application.

Comments